If we are halfway through implementation and behind plan, then do we move the audit date?

4 decision pointsThe pack behind this answer: ISO 27001 Implementation & Certification Readiness

Add to board memo

The short answer

Recommendation
Do not move the date because gates are late. Re-forecast the earliest Stage 2 date from your current gaps and compare it with the booked date. Keep the date if it fits; if the margin is thin, tell the executive sponsor and watch the critical path weekly; if it does not fit, the sponsor decides that month whether to add resource, narrow the scope or move the date.
Reasoning
Late gates show the plan was optimistic. They do not show whether the audit date fails; only a fresh forecast does. The earliest Stage 2 date is the latest of three: the last gap In place, the last blocking item In place plus the operating period (IS-05), and the internal audit and management review done. That is why a late blocking item matters far more than a late ordinary control. Adding people shortens the work of putting gaps In place, but not the months of records after it. In the pack's worked example the firm is weeks behind at two gates, yet its forecast still falls 18 calendar days inside the booking.
Considerations
  • The 3-month operating period, the 4-week margin trigger and the 8 to 12 weeks' lead time are the pack's defaults. Your certification body may expect a longer operating period.
  • Narrow the scope only if it still passes every scope test. A scope cut only to leave out what is not ready fails them, and narrowing after Stage 1 is expensive.
  • Any scope change needs top management's approval: the board or a committee it has delegated to, the management board in a two-tier structure, or executive management where there is no board.
  • If the date must move, move it early and with the certification body's agreement. Moving Stage 2 is better than going in expecting a major nonconformity.

The decision, step by step

Select any step for the reasoning behind it and where the pack covers it.

  • Start
  • Step
  • Decision
  • Outcome

Keyboard: Tab to a step, arrow keys move along the flow, Enter pins its explanation, + and − zoom, 0 fits the diagram, Esc closes. The text version below has the same content.

Where a step quotes a number, it is the default in the CISO Times pack. Your own standard may set a different one.

Read as text

The same flow written out: each step, its reasoning and where the pack covers it. 14 steps.
  1. Start

    Halfway through, and gates are coming in late

    A first certification that runs late is common: the scope takes longer to approve, the Statement of Applicability slips, controls are not yet producing records. Late gates tell you the plan was optimistic. They do not yet tell you whether the audit date fails. Only a fresh forecast does.

    In the pack

  2. Step

    Rescore readiness honestly, and have the blockers checked

    Score every requirement from 0 (Not started) to 3 (Operating), taking the lower score when in doubt. Have a second person check the blocking items, since owners tend to score their own controls high. Being behind plan is exactly when optimism costs most.

  3. Step

    Give every gap an owner and real weeks of work

    Each gap needs an owner and the weeks of work that owner can actually give it, with blocking items first in every queue. In a small organisation the ISMS manager's queue is nearly always the critical path. An overdue gap on the critical path is the first thing to raise with the executive sponsor.

  4. Step

    Re-forecast the earliest Stage 2 date

    Take the latest of three dates: (a) the last gap In place, with owners working one gap at a time; (b) the last blocking item In place plus the operating period, 3 months by the pack's default; (c) the internal audit and management review done. In the pack's worked example, (b) sets the date. That is why a late blocking item matters far more than a late ordinary control.

  5. Decision

    Does the forecast fall on or before the booked Stage 2 date?

    Compare the forecast with the booked Stage 2 date, not with the original plan. In the pack's worked example the firm is weeks behind at two gates, yet its forecast still falls 18 calendar days inside the booking. If you cannot produce a forecast you trust, answer no.

    In the pack

  6. Decision

    Is the margin under 4 weeks, or a blocker undated?

    The pack's trigger for taking it to the executive sponsor is a forecast within 4 weeks of the booked Stage 2 date, or any blocking item with no date before Stage 2. A small margin is not a failure, but one slipped gap on the critical path will use it up. If you are unsure, answer yes.

    In the pack

  7. Outcome

    Keep the date; re-date the missed gates and report monthly

    Re-date each missed gate rather than declaring it met. Report the headline measures to top management every month and recompute the forecast each time. Move the date later only if a future forecast says so.

    In the pack

  8. Outcome

    Keep the date: tell the sponsor and watch the critical path weekly

    This is where the pack's worked example lands: behind plan, but with a forecast 18 calendar days inside the booking. The executive sponsor is told that month, each critical-path gap is reviewed weekly in the gap tracker, and the missed gate is re-dated rather than declared met. If the next forecast slips past the booking, the sponsor decides then.

    In the pack

  9. Step

    Take it to the executive sponsor this month

    Do not wait for Stage 1 to decide for you. The sponsor chooses between adding resource, narrowing the scope and moving the date. If a customer, tender or regulator set the deadline, say plainly whether the forecast meets it.

    In the pack

  10. Decision

    Would more people bring the forecast inside the booking?

    More people only shorten the work of putting gaps In place: date (a), and date (b) if they get the last blocking item In place sooner. They cannot shorten the months of records after it. The implement-and-operate phase is the time controls need to run, and adding people does not compress it. If you cannot tell, answer no.

  11. Outcome

    Add resource to the critical path and keep the date

    Put the extra effort on the gaps whose slip would move the date: the critical path, starting with the blocking items. Review those gaps weekly in your gap tracker. Release the time from other work: internal effort that is added on top of people's day jobs is why projects slip while controls are being put in place.

  12. Decision

    Can the scope narrow and still pass the scope tests?

    A narrower scope only works if every exclusion has a real reason, nothing in scope depends on what is excluded, and customers still recognise the service they buy. A service that will not have run for the operating period by Stage 2 can be added later at a surveillance audit. Narrowing after Stage 1 is expensive. Top management must approve any change to the scope.

    In the pack

  13. Outcome

    Narrow the scope through top management, before Stage 1

    Take the revised scope statement to top management for approval, with what it now leaves out and why. Depending on how you are governed, that is the board or a committee it has delegated to, the management board in a two-tier structure, or executive management where there is no board. Update the risk assessment and the Statement of Applicability to match, then re-run the forecast. Plan to widen the scope at a later surveillance audit.

    In the pack

  14. Outcome

    Move the date now, with the certification body

    Move early and deliberately. Agree new dates with the certification body, allowing for its lead time, which the pack puts at 8 to 12 weeks. Keep Stage 1 and Stage 2 close enough that Stage 1 stays current. Moving Stage 2 is better than going in expecting a major nonconformity.

Practical checklist

  1. Rescore readiness honestly, taking the lower score when in doubt, and have a second person check the blocking items.
  2. Give every gap an owner and the weeks of work they can actually give it, blocking items first.
  3. Re-forecast the earliest Stage 2 date as the latest of the three dates.
  4. Compare the forecast with the booked Stage 2 date, not with the original plan.
  5. If it fits with margin, keep the date, re-date the missed gates and report the headline measures monthly.
  6. If the margin is under 4 weeks or a blocker is undated, tell the sponsor and review critical-path gaps weekly.
  7. If it does not fit, take it to the sponsor this month: add resource to the critical path, narrow the scope, or move the date.

Evidence to have ready

  • This month's readiness reassessment, with the second person's check of the blocking items.
  • The gap tracker, with owners, weeks of work and the critical path.
  • The forecast worked out step by step, against the booked Stage 2 date.
  • The monthly headline measures reported to top management (IS-10).
  • The sponsor's decision, and any approved scope change or dates agreed with the certification body.

Assumptions

  • You have a certification body booking, or a target date, and a plan with phases and gates.
  • The operating period, margins and lead times shown are the CISO Times ISO 27001 pack's defaults. Your certification body may expect a longer operating period.

Not covered here