The short answer
- Recommendation
- Write a short top-level policy for top management to approve, with the commitments the standard asks for. Set five to ten measurable objectives with owners and dates, and write topic policies only for the controls you chose.
- Reasoning
- Auditors read the policy and the objectives at the top of the system. The usual gaps are a policy with no objectives or way to set them, no commitment to improve, a signature from someone other than top management, a policy staff cannot reach, and objectives nobody measures. Writing a full policy set before the controls are chosen produces documents nobody runs, which the auditor then samples.
- Considerations
- The standard's wording is paywalled. The content of the policy here comes from public secondary guides and the pack's checklist, so confirm it with your certification body.
- A combined policy with an information security section can serve, if it carries the commitments and is communicated.
- Objectives that cannot be measured, or that nobody monitors, are a common finding. Reword them until a figure or a yes or no test can show them.
- The pack's defaults are five to ten objectives and a review at least every 12 months. Your own procedure may set others.
The decision, step by step
Select any step for the reasoning behind it and where the pack covers it.
- Start
- Step
- Decision
- Outcome
Keyboard: Tab to a step, arrow keys move along the flow, Enter pins its explanation, + and − zoom, 0 fits the diagram, Esc closes. The text version below has the same content.
Where a step quotes a number, it is the default in the CISO Times pack. Your own standard may set a different one.
Read as text
The same flow written out: each step, its reasoning and where the pack covers it. 22 steps.
Start
We need an information security policy and objectives for ISO 27001
The policy and the objectives are among the eight items without which the pack says a Stage 2 audit cannot pass. Top management establishes them, and they come early in the plan: the policy direction is approved at the first gate, and the objectives are set when the controls are chosen.
In the pack
- P08-A02 ISO 27001 Implementation Methodology & Project PlanBlocking items
- P08-A02 ISO 27001 Implementation Methodology & Project PlanPhase 3 — Select and document controls (6 weeks)
Decision
Does a top-level information security policy already exist?
Many organisations already have one. Reuse it if it can be made to fit rather than starting again. If you are not sure it is current or approved, answer no.
- Yes: Check the existing policy against what auditors find missing
- No, or not known: Write a short top-level policy
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-02)
Step
Write a short top-level policy
A short policy signed by top management, with topic-specific policies beneath it. Keep it to direction and commitments: what the organisation intends and why, leaving rules and steps to the documents below. Use the policy template to keep the form consistent.
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-02)
- P04-A04 Security Policy Document TemplatePart 1 — How to write a policy with this template
Step
Check the existing policy against what auditors find missing
The pack lists the usual gaps: no objectives or framework for setting them, no commitment to continual improvement, signed by someone other than top management, not available to the people it applies to, and a review date that has passed.
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-02)
Decision
Does it fit your purpose, carry the commitments and set objectives?
Public guides to the standard describe four contents: fit with the organisation's purpose, a commitment to meet the requirements that apply, a commitment to continual improvement, and either objectives or a framework for setting them. If any is missing or unclear, answer no.
- Yes: Is it approved and signed by top management, not by the security team?
- No, or not known: Add the missing commitments and the objectives framework
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-02)
Step
Add the missing commitments and the objectives framework
Say in plain sentences what the organisation commits to, and say how objectives are set and who sets them. A combined policy with an information security section is accepted if it carries these commitments and is communicated.
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-02)
Decision
Is it approved and signed by top management, not by the security team?
A policy signed by someone other than top management is one of the gaps the pack lists. Top management here means the board or a committee it has delegated to, the management board in a two-tier structure, or executive management where there is no board. If unsure, answer no.
- Yes: Communicate it and make it easy to reach
- No, or not known: Take it to top management for approval and record the date
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-02)
- P04-A02 Policy Framework StandardApproval
Step
Take it to top management for approval and record the date
Present the policy as a decision, not a circulation. Record who approved it and when, give it a version and a review date, and keep the approval under document control.
In the pack
- P04-A02 Policy Framework StandardApproval
- P08-A02 ISO 27001 Implementation Methodology & Project PlanPhase 3 — Select and document controls (6 weeks)
Step
Communicate it and make it easy to reach
Publish it in one place staff can reach, get it acknowledged, and review it at least every 12 months or after a significant change. Auditors may ask staff where it is. Public guides also expect it to be available to interested parties where that is appropriate.
In the pack
- P08-A03 Annex A Control Implementation LibraryControl Library
- P04-A02 Policy Framework StandardAcknowledgement
Decision
Is the Statement of Applicability approved?
Only the controls you choose need documents. Writing a full policy set first produces documents nobody runs, which the auditor then samples. If the Statement is not yet approved, answer no.
- Yes: Write only the topic policies your chosen controls need
- No, or not known: Hold the topic policies until the controls are chosen
In the pack
- P08-A02 ISO 27001 Implementation Methodology & Project PlanSequencing that avoids rework
- P08-A02 ISO 27001 Implementation Methodology & Project PlanCommon failure modes
Step
Hold the topic policies until the controls are chosen
Keep the top-level policy now and write the topic policies after the controls are chosen. Do not buy a toolkit of dozens of policies describing processes nobody runs. Come back and write the topic policies once the Statement is approved.
In the pack
- P08-A02 ISO 27001 Implementation Methodology & Project PlanSequencing that avoids rework (rule IS-03)
- P08-A02 ISO 27001 Implementation Methodology & Project PlanCommon failure modes
Step
Write only the topic policies your chosen controls need
Use the policy profile to decide which topics your size, regulators and certification target call for, and write the rest only if a control needs them. Each must be short, testable and owned.
In the pack
- P08-A02 ISO 27001 Implementation Methodology & Project PlanPhase 3 — Select and document controls (6 weeks)
- P04-A04 Security Policy Document TemplateWriting testable "must" statements
Step
Set five to ten objectives
Each objective has a measure, a target, an owner, the resources, a date and how the result is evaluated. Take them from your risk results where you have them, and from the requirements that apply, and keep them consistent with the policy. Top management sets them.
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-07)
- P08-A02 ISO 27001 Implementation Methodology & Project PlanPhase 3 — Select and document controls (6 weeks)
Decision
Can each objective be measured by something you can collect?
The pack and auditors expect objectives that can be measured or tested; an unmeasured one is a common finding. If no figure or yes or no test can show whether it was met, or you are not sure the data exists, answer no.
- Yes: Start measuring when the controls run, and report upward
- No, or not known: Reword it until a figure or a clear test can show it
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-07)
Step
Reword it until a figure or a clear test can show it
Change the objective, or the measure, so the data exists. Drop the objective if no honest measure can be found.
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-07)
Step
Start measuring when the controls run, and report upward
Begin measuring in the implementation phase. Keep dated results, analyse them, and take the trend to top management at the management review, since the certification body expects to see the objectives monitored.
In the pack
- P08-A02 ISO 27001 Implementation Methodology & Project PlanPhase 4 — Implement and operate (12 weeks)
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-13)
- P08-A09 Management Review Meeting PackThe pre-read pack, with owners
Decision
Do the people who deliver each objective know it?
Objectives must be communicated to the people who deliver them. If you have not told them, or cannot show that you did, answer no.
- Yes: Review the policy and objectives at the planned interval
- No, or not known: Tell the owners and the teams, and keep a record
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-07)
Step
Tell the owners and the teams, and keep a record
Send the objectives to their owners and delivery teams in a short note or briefing, and keep it. Repeat when an objective changes.
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rule MD-07)
Step
Review the policy and objectives at the planned interval
Review at least every 12 months, after a significant change, and when the management review calls for it. Update the version and keep the record of the review.
In the pack
- P08-A03 Annex A Control Implementation LibraryControl Library
- P08-A09 Management Review Meeting PackThe decisions to record
Decision
Are topic policies still waiting for the Statement of Applicability?
If the Statement was not approved when you reached the topic policies, they are still to write. Write only the ones the chosen controls need. If you are not sure, answer yes.
- Yes, or not known: Write the topic policies the chosen controls need
- No: Policy approved, objectives set and measured: keep the records
In the pack
- P08-A02 ISO 27001 Implementation Methodology & Project PlanSequencing that avoids rework
Step
Write the topic policies the chosen controls need
Once the Statement of Applicability is approved, write and approve only the topic policies its controls call for, in the same short testable form.
In the pack
- P08-A02 ISO 27001 Implementation Methodology & Project PlanPhase 3 — Select and document controls (6 weeks)
- P04-A04 Security Policy Document TemplateWriting testable "must" statements
Outcome
Policy approved, objectives set and measured: keep the records
Keep the approved policy, the acknowledgement records, the objectives and their measurement results as controlled records. Certification bodies read the policy and objectives at Stage 1 and sample the records at Stage 2.
In the pack
- P08-A05 Mandatory ISMS Documentation ChecklistRequired Documents (rules MD-02, MD-07)
- P08-A10 Stage 1 and Stage 2 Audit Preparation GuideThe two stages at a glance
Practical checklist
- Check any existing policy for the commitments, the objectives framework and a top management signature.
- Have top management approve the top-level policy and record the date.
- Publish it where staff can reach it and keep acknowledgement records.
- Wait for the Statement of Applicability, then write only the topic policies the chosen controls need.
- Set five to ten objectives with a measure, target, owner, resources and date each.
- Start measuring when the controls run, and report the results at the management review.
Evidence to have ready
- The approved policy with its version, approval date and next review date.
- Acknowledgement records for a sample of staff.
- The objectives record with measures, owners and dates.
- Measurement results and the management review minutes that discuss them.
Assumptions
- The scope is approved, or about to be, because the policy and objectives apply within it.
- The risk assessment has produced results to draw objectives from, or will before you finalise them.
- You aim to certify against ISO/IEC 27001:2022, or want a policy set that would stand an audit against it.
- The number of objectives and the 12-month review interval are the CISO Times pack's defaults. Your own procedure may set different ones.
Not covered here
- Which topic policies your size and regulators call for. That is “How do we decide which policies we actually need, for our size and regulation?”.
- Writing a policy statement an auditor can test. That is “How do we write a policy statement that an auditor can test?”.
- Who approves each tier of document. That is “Who approves a policy, a standard and a procedure?”.
- Getting staff to acknowledge policies. That is “How do we get staff to acknowledge policies, and chase those who don't?”.
Related questions
- How do we write a policy statement that an auditor can test?
- How do we decide which policies we actually need, for our size and regulation?
- Who approves a policy, a standard and a procedure?
- How do we get the top management commitment and resources an ISO 27001 project needs?
- How do we decide what to monitor and measure in our ISMS, and who evaluates it?
- How do we decide what documented information our ISMS needs and keep it under control?