Who decides…
Who should test our controls when the team is too small to be independent?
Add to board memoOpen the memo
The short answer
- Recommendation
- Keep the rule that no one tests a control they own, perform, manage or wrote, and look outside the team: a colleague who already checks records, a swap between people or teams, internal audit, then a contracted tester or a peer. Record any owner's own check as a self-check, with the control still untested.
- Reasoning
- This is the internal audit rule applied to a control test (rule CA-10). In a small organisation the person who knows the controls best usually runs them, so the security lead often tests none of them. A colleague from quality, finance, HR or compliance needs the control's statement, attributes and evidence standards, not security expertise. Someone else must also review every workpaper, or the conclusion is not final (rule CA-11).
- Considerations
- An owner's check is worth doing and can warn you to bring a test forward. It never replaces a planned test because no one else was free.
- The pack sets no terms of its own for an outside tester. Agree in writing that they have not designed, run or advised on the controls they test, and agree confidentiality.
- Review within 10 working days of the last test step is the pack's default.
- If an audit, a regulator or a customer will rely on the testing, confirm with them the independence they expect.
The decision, step by step
Select any step for the reasoning behind it and where the pack covers it.
- Start
- Step
- Decision
- Outcome
Keyboard: Tab to a step, arrow keys move along the flow, Enter pins its explanation, + and − zoom, 0 fits the diagram, Esc closes. The text version below has the same content.
Where a step quotes a number, it is the default in the CISO Times pack. Your own standard may set a different one.
Read as text
The same flow written out: each step, its reasoning and where the pack covers it. 13 steps.
Start
Every control needs a tester who neither owns nor performs it
This is P08's rule that internal auditors must not audit their own work, applied to a control test, as the maturity pack applies it to an assessment. In a small organisation the person who knows the controls best usually runs them. The Head of Information Security owns most of the security controls, and so tests none of them.
In the pack
- P20-A02 Control Testing MethodologyWho may test (rule CA-10)
- P08-A08 ISMS Internal Audit Programme & ProcedureIndependence (rule IS-07)
- P19-A03 Internal Security Assessment ProcedureThe rule (rule MA-14)
Step
List who owns, performs, manages and wrote each control
A control is your own if you own it, carry it out, manage the people who carry it out day to day, or wrote the procedure it follows. Anyone in any of those positions for a control may not test it. The performer shows the tester the records and takes no other part in the test.
In the pack
- P20-A05 Control Test Execution ProcedureStage 1: Plan the test (rule CA-10)
- P20-A05 Control Test Execution ProcedureRoles
Step
Name an assurance lead who owns and performs no control in scope
The lead keeps the inventory and the plan, assigns testers and reviews the workpapers they did not write, so every workpaper has someone independent to review it. A quality and compliance manager, a risk manager or internal audit often fits.
In the pack
- P20-A02 Control Testing MethodologyWho is involved
- P20-A02 Control Testing MethodologyWho may test (rule CA-10)
Decision
Is there a colleague in another function who runs none of them?
A colleague who already checks records, such as a quality, finance, HR or compliance manager, is often the best choice. They need the control's statement, its attributes and the evidence standards, not security expertise. Someone who asks to be shown the record and waits for it often finds more than a specialist who already knows the answer.
- Yes: Assign the tester and record which option you used
- No, or not known: Can people or teams test each other's controls, never their own?
In the pack
- P20-A05 Control Test Execution ProcedureRoles (rule CA-10)
- P08-A08 ISMS Internal Audit Programme & ProcedureCompetence
Decision
Can people or teams test each other's controls, never their own?
Where controls are split between people or teams, such as the security team and the IT team, each can test the other's. Check the swap against your list: no one tests a control they own, perform, manage or wrote.
- Yes: Assign the tester and record which option you used
- No, or not known: Do you have internal audit with time to test?
In the pack
- P20-A02 Control Testing MethodologyWho may test (rule CA-10)
- P19-A03 Internal Security Assessment ProcedureWays to stay independent, in the order to try them (rule MA-14)
Decision
Do you have internal audit with time to test?
The pack names internal audit as a tester, and as the reviewer of the assurance lead's own tests. If you have no internal audit function, or it cannot take the work this cycle, answer No.
- Yes: Assign the tester and record which option you used
- No, or not known: Can you contract a tester, or use a peer from another organisation?
In the pack
- P20-A02 Control Testing MethodologyWho may test (rule CA-10)
Decision
Can you contract a tester, or use a peer from another organisation?
P20 sets no terms of its own for an outside tester; the audit and maturity packs' terms fit. Agree in writing that they have not designed, run or advised on the controls they test, keep a record of their competence, and agree confidentiality and what happens to the evidence at the end. A consultant who helped build a control should not test what they built.
- Yes: Assign the tester and record which option you used
- No: Record any owner's check as a self-check: the control stays untested
In the pack
- P08-A08 ISMS Internal Audit Programme & ProcedureCompetence
- P19-A03 Internal Security Assessment ProcedureA contracted or reciprocal assessor
- P20-A05 Control Test Execution ProcedureRoles (rule CA-10)
Step
Assign the tester and record which option you used
Record on the workpaper that the tester and the reviewer have both checked their independence. Brief a tester from outside security on the control's statement, attributes and evidence standards. The performer shows the records and takes no other part; the owner never chooses the sample. The same rule applies to a retest after a deficiency is fixed.
In the pack
- P20-A05 Control Test Execution ProcedureStage 1: Plan the test (rule CA-10)
- P20-A02 Control Testing MethodologyRetest and closure (rule CA-14)
Decision
Is there a reviewer who did not do the test?
Someone other than the tester reviews every workpaper. The assurance lead reviews the tests they did not write; where the lead tests, someone else reviews, such as internal audit. If no one is lined up, take the cautious branch.
- Yes: Test it, and have the reviewer sign within 10 working days
- No, or not known: Not final: find a reviewer before you report a result
In the pack
- P20-A02 Control Testing MethodologyThe workpaper and its review (rule CA-11)
- P20-A05 Control Test Execution ProcedureRoles
Outcome
Test it, and have the reviewer sign within 10 working days
The pack's default is review within 10 working days of the last test step. The conclusion is final only when the reviewer signs, and any deficiency is confirmed that day.
In the pack
- P20-A05 Control Test Execution ProcedureStage 8: Review and sign the workpaper (rule CA-11)
Outcome
Not final: find a reviewer before you report a result
A workpaper still unsigned 10 working days after the last test step is overdue, and the dashboard counts the control as untested. The tester raises it with the assurance lead. Who reviews instead is your decision; the pack names internal audit as the reviewer of the lead's own tests.
In the pack
- P20-A02 Control Testing MethodologyThe workpaper and its review (rule CA-11)
- P20-A05 Control Test Execution ProcedureDeficiencies past their due date (rule CA-11)
Step
Record any owner's check as a self-check: the control stays untested
An owner who checks their own control is doing their job, and it is worth doing. It is not a test. Record it with who made it, keep the control untested in the inventory and on the dashboard, and use what it found: an exception the owner found is a warning to bring the test forward.
In the pack
- P20-A05 Control Test Execution ProcedureA check made by the control owner (rule CA-10)
Outcome
Take a proposal for an independent tester to the assurance sponsor
Never let a self-check replace a planned test because there was no one else to do it. The assurance lead escalates to the sponsor with a proposal: a colleague from another function, internal audit or a contracted tester.
In the pack
- P20-A05 Control Test Execution ProcedureDeficiencies past their due date (rule CA-10)
- P20-A05 Control Test Execution ProcedureA check made by the control owner (rule CA-10)
Practical checklist
- List who owns, performs, manages and wrote each control.
- Name an assurance lead who owns and performs no control in scope.
- Try a colleague from another function, then a swap, then internal audit, then a contracted tester or peer.
- Brief a tester from outside security, and keep the performer to showing the records.
- Line up a reviewer who did not do the test before reporting any result.
- Record an owner's own check as a self-check, and keep the control untested.
- Take a proposal for an independent tester to the assurance sponsor where none is available.
Evidence to have ready
- The workpaper recording the tester, the option used and both tester's and reviewer's independence checks.
- The written terms with any outside tester.
- The reviewer's signature and date on every workpaper.
- Self-checks recorded as such, with the control shown untested on the dashboard.
Assumptions
- Each control has a written statement and a list of attributes, so a tester who is not a security specialist can check it against the records.
- A member of management sponsors control testing and can ask colleagues outside security to give time to it.
- This is testing for your own assurance. If an audit, a regulator or a customer will rely on it, confirm with them the independence they expect.
Not covered here
- Who should assess your security practices for a maturity rating. That is “Who should assess our security practices when the team is too small to be independent?”.
- Who may carry out the ISO/IEC 27001 internal audit in a small organisation. That is “How do we run an internal audit when we are small?”.
- Whether to commission a fully independent assessment instead. That is “When should we commission an independent assessment instead of self-assessing?”.
- Separating duties when one administrator also runs the controls over their own work. That is “If the only IT administrator also manages the security logs, then how do we control that?”.
Related questions
- Who should assess our security practices when the team is too small to be independent?
- How do we run an internal audit when we are small?
- When should we commission an independent assessment instead of self-assessing?
- If the only IT administrator also manages the security logs, then how do we control that?