When does a risk need reassessing outside the annual cycle?

3 decision pointsThe pack behind this answer: Information Security Risk Management

Add to board memo

The short answer

Recommendation
Reassess a risk outside the annual cycle whenever a trigger touches it, within 10 working days in the pack's defaults, and before go-live for a major change where you can. If its position against appetite changes, the notices and decisions for the new position follow at once.
Reasoning
The quarterly owner review and the yearly reassessment keep the register broadly current, but some events change a risk too much to wait. There are six triggers: a major incident or a revealing near miss; a major change; a new or changed threat; an audit, test or assessment finding; a change in law, regulation or a key contract; and a control that has failed or does not work as assumed. One trigger often touches several risks. A change assessed before go-live can still be adjusted; once live, the assessment can only describe the risk you carry.
Considerations
  • The 2 and 10 working days, the 30-day treatment window and the 5 working days to the chair are the defaults in the CISO Times risk management pack. Your own procedure may set different ones.
  • If you are unsure whether an event is a trigger, treat it as one.
  • A risk now outside tolerance, or any Critical residual risk, can be accepted only by the board or its equivalent: the board or its delegated risk committee, the management board in a two-tier structure, or executive management where there is no board.
  • A risk newly outside appetite keeps its treatment window from the date it was first assessed outside appetite. Later reviews do not restart it.

The decision, step by step

Select any step for the reasoning behind it and where the pack covers it.

  • Start
  • Step
  • Decision
  • Outcome

Keyboard: Tab to a step, arrow keys move along the flow, Enter pins its explanation, + and − zoom, 0 fits the diagram, Esc closes. The text version below has the same content.

Where a step quotes a number, it is the default in the CISO Times pack. Your own standard may set a different one.

Read as text

The same flow written out: each step, its reasoning and where the pack covers it. 11 steps.
  1. Start

    Something has happened since the risk was last assessed

    A yearly reassessment and a quarterly owner review keep the register broadly current. Between them, some events change a risk too much to wait. Those events are triggers, and a trigger sets its own deadline.

    In the pack

  2. Decision

    Is the event one of the triggers?

    The triggers: a major incident, or a near miss that shows a risk was underrated; a major change to systems, processes, suppliers or the organisation; a new or changed threat relevant to your services; an audit, test or assessment finding; a change in law, regulation or a key contract; a control that has failed, or is found not to work as the assessment assumed. If you are unsure whether it qualifies, treat it as a trigger.

    In the pack

  3. Outcome

    Leave it for the owner's quarterly review

    Smaller changes are picked up at the quarterly owner review, which asks whether the scenario is still right, the controls still work, the actions are on time, and anything has changed the ratings. A risk not reviewed by quarter end is escalated to the owner's line executive and named in the quarterly report.

    In the pack

  4. Step

    Record the trigger and list the risks it touches

    Within 2 working days of hearing of it, in the pack's defaults, note the trigger, its date, and every register entry it affects. One incident or change often touches several risks. If it suggests a scenario the register lacks, raise it as a new risk.

    In the pack

  5. Decision

    Is it a major change that has not gone live yet?

    A change can be assessed while it can still be adjusted. Once live, the assessment can only describe the risk you now carry.

    In the pack

  6. Step

    Assess the touched risks before go-live where possible

    Run the reassessment as part of the change, and keep it with the change record. Regulated entities are expected to assess risk on each major change, so this record is also their evidence.

    In the pack

  7. Step

    Reassess each touched risk with its owner, within 10 working days

    Rate impact and likelihood again, inherent and residual, with a reason for each change. An incident may confirm the threat is real, or show a control worked where it was in place. Count only controls with evidence. If the deadline passes, the assessor escalates to the Head of Information Security.

    In the pack

  8. Decision

    Has the risk's position against appetite changed?

    Read the new residual band against the category's appetite and tolerance. The position is one of three: within appetite; outside appetite, within tolerance; outside tolerance. A Critical residual risk is always outside tolerance.

    In the pack

  9. Outcome

    Update your register with the new ratings and date

    Record the reassessment date and the new ratings with reasons, even if nothing moved. A risk that returned within appetite is reported to executive management as movement at the next quarterly report.

    In the pack

  10. Outcome

    Tell the people its band requires, and decide treatment

    Notify the people the new band requires. A risk newly outside appetite needs a treatment decision by its owner within 30 calendar days of first being assessed outside appetite, in the pack's defaults. Later reviews do not restart that window.

    In the pack

  11. Outcome

    Tell the board chair out of cycle

    A risk now outside tolerance, or any Critical residual risk, goes to the board chair without waiting for the next meeting, within 5 working days in the pack's defaults. Only the board or its equivalent may accept it: the board or its delegated risk committee, the management board in a two-tier structure, or executive management where there is no board.

    In the pack

Practical checklist

  1. Decide whether the event is one of the six triggers. Leave smaller changes to the owner's quarterly review.
  2. Record the trigger and every register entry it touches within 2 working days, and raise any new scenario it suggests.
  3. For a major change not yet live, run the reassessment as part of the change.
  4. Reassess each touched risk with its owner within 10 working days, counting only controls with evidence.
  5. Read the new position against the category's appetite and tolerance.
  6. Notify the people the new band requires, and get a treatment decision for a risk newly outside appetite.
  7. Tell the board chair out of cycle about a risk now outside tolerance or Critical.

Evidence to have ready

  • The trigger record: what happened, when, and the risks it touched.
  • The reassessment date and new ratings with reasons, recorded even where nothing moved.
  • For a major change, the risk assessment kept with the change record.
  • Notices sent and treatment decisions made where the position changed.

Assumptions

  • Owners already review each risk every quarter and the whole register is reassessed once a year.
  • The timings shown are the defaults in the CISO Times risk management pack. Your own procedure may set different ones.

Not covered here