How do we build a risk register from nothing?

4 decision pointsThe pack behind this answer: Information Security Risk Management

Add to board memo

The short answer

Recommendation
Agree one scoring method and a short list of categories first. Then pick, from a library of ready-written scenarios, the ones that can happen to your key services, reword them for your own services, give each one executive owner, score them before and after working controls, and enter each once in a single register.
Reasoning
A blank page produces topics, and topics cannot be owned or scored. Starting from written scenarios and the services the business cannot do without gives risks someone can own. Scoring before the scale is fixed means scoring everything twice. Keeping risks you think are well controlled shows they were considered. A short register that owners actually review beats a long one nobody does. Testing the appetite against the register shows whether the levels or the scores are wrong before the board approves them.
Considerations
  • The figures are the defaults in the CISO Times risk management pack: 10 to 15 risks for a small organisation, usually five to eight categories, and 30 days for a treatment decision. Your own method may set different ones.
  • The appetite is approved by the board, or a board risk committee it has delegated to; the management board in a two-tier structure; executive management where there is no board.
  • A library's starting scores are typical levels, not your assessment. Only controls with evidence that they work lower a score.
  • In a small organisation one person may assess every risk, but each still needs an owner outside the security role.

The decision, step by step

Select any step for the reasoning behind it and where the pack covers it.

  • Start
  • Step
  • Decision
  • Outcome

Keyboard: Tab to a step, arrow keys move along the flow, Enter pins its explanation, + and − zoom, 0 fits the diagram, Esc closes. The text version below has the same content.

Where a step quotes a number, it is the default in the CISO Times pack. Your own standard may set a different one. A code beside a source, such as RR-17, is the number of a rule in that pack document; the document lists its rules.

Read as text

The same flow written out: each step, its reasoning and where the pack covers it. 18 steps.
  1. Start

    There is no risk register yet

    Starting from a blank page tends to produce a list of topics: 'ransomware', 'phishing', 'GDPR'. Topics cannot be owned or scored. Start instead from a library of scenarios already written in the right form, and from the services the business cannot do without.

    In the pack

  2. Decision

    Is there an agreed method for scoring risks?

    The method sets the impact and likelihood scales, the bands and who may accept each band. If an enterprise risk scale already exists, it counts. If nobody can point to an approved one, answer no.

  3. Step

    Adopt one scoring method before scoring anything

    Keep one scale for all risks: four levels of impact and likelihood, a matrix and four bands. If finance or enterprise risk already has a scale, use its money thresholds so 'Severe' means the same everywhere. Scoring first and fixing the scale later means scoring everything twice.

  4. Step

    Choose a short list of risk categories

    Categories group risks that share one appetite, such as service availability, customer and personal data, financial fraud, regulatory compliance, third-party dependency, and people and insider. Keep few enough for the board to hold in mind, usually five to eight. Every risk will sit in exactly one.

    In the pack

  5. Step

    List the services the business depends on

    List the services and assets that matter, how critical each is, and the executive accountable for it. That executive is usually the owner of the risks to it. In a small organisation, start with your two or three most important services.

    In the pack

  6. Step

    Pick the library scenarios that can happen to you

    Filter a scenario library by category, threat and where each applies. Leave out scenarios that cannot happen to you. Keep the ones that can, even if you think they are well controlled: the register should show that a risk was considered and is under control, not only that it is high. A category with nothing picked deserves a second look.

    In the pack

  7. Step

    Add what your own sources already show

    Go through recent incidents and near misses, audit and penetration test findings, open security exceptions, threat reports relevant to your sector, planned changes, and concerns staff have raised. Each may add a scenario the library lacks, or show that one you picked is more likely than its starting score.

    In the pack

  8. Step

    Reword each scenario for your own service

    Each risk needs four parts: threat, weakness, asset or service, and consequence. Name your own service, system or supplier. A scenario naming a real asset is a risk someone can own; a generic one is not.

    In the pack

  9. Step

    Name one executive owner for each risk

    The owner is the executive accountable for the service or asset the risk would hurt, by role. Not the security team, which assesses and advises. Security owns a risk only where the harm falls on its own duties. In a small organisation one person may assess every risk, but each still needs an owner outside the security role.

    In the pack

  10. Decision

    Is the list short enough for owners to review every quarter?

    Every risk is reviewed by its owner every quarter. For a small organisation the pack suggests 10 to 15 well-owned risks, which are better than 50 nobody reviews. If the list has grown past what owners will actually review, answer no.

    In the pack

  11. Step

    Merge scenarios that are really one risk

    Several entries on one service often describe the same event. Merge them into one scenario scored at its worst consequence, and note which entries it replaces. Several scenarios often share one cure, such as multi-factor sign-in or tested backups, so one action may reduce many risks.

    In the pack

  12. Step

    Score each risk before and after controls that work

    A library's starting scores are typical levels, not your assessment. Rate impact on the worst consequence and likelihood over the next 12 months, first with no specific controls, then with the controls you have evidence for. A control without evidence does not count. A workbook per service keeps the working, and its result goes into the register.

    In the pack

  13. Step

    Enter each risk once, in a single register

    Give each risk a reference that never changes. Record the scenario, owner, category, ratings with reasons, controls, band and position. The register is the only record of assessed risks: the library and workbooks are sources, not second lists to maintain. Copy their results in as values.

    In the pack

  14. Decision

    Has the board approved an appetite for each category?

    Without an appetite, nobody can say whether a risk is acceptable. Who approves depends on how you are governed: the board, or a board risk committee it has delegated to; the management board in a two-tier structure; executive management where there is no board. If it is only in draft, answer no.

    In the pack

  15. Step

    Test a draft appetite against the register, then seek approval

    Ask each category's owner which harm the organisation would not accept even for a clear benefit, and pick Averse, Cautious or Open. Test the draft against the new register. If most risks land outside appetite, the level or the scores are wrong. If nothing lands outside in a category the board worries about, the level may be too loose. Send the result with the draft.

    In the pack

  16. Decision

    Is any risk outside its category's appetite?

    Compare each risk's residual band with its category's appetite and tolerance. The answer is a count: how many risks are outside appetite, and how many of those are past tolerance.

    In the pack

  17. Step

    Get a treatment decision for each one outside appetite

    The owner decides to reduce, avoid, transfer or accept, within 30 calendar days of the risk first being assessed outside appetite in the pack's defaults. A risk past tolerance goes to the board chair out of cycle.

    In the pack

  18. Outcome

    A working register: reviewed quarterly, reassessed yearly

    From here the register is kept current by routine. Each owner reviews their risks every quarter, the whole register is reassessed once a year, and triggers such as a major incident or change force an earlier reassessment. The position against appetite is reported to executive management every quarter.

    In the pack

Practical checklist

  1. Adopt one scoring method, using finance's money thresholds where they exist.
  2. Choose a short list of risk categories, each with one appetite.
  3. List the services the business depends on, with their criticality and accountable executive.
  4. Pick the library scenarios that can happen to you, and add what incidents, audits and exceptions already show.
  5. Reword each for your own service and name one executive owner.
  6. Merge scenarios that are really one risk, then score each before and after controls that work.
  7. Enter each risk once in a single register with a reference that never changes.
  8. Test a draft appetite against the register, seek approval, and get a treatment decision for each risk outside it.

Evidence to have ready

  • The approved scoring method and the list of categories with their approved appetite.
  • The register, with each risk's scenario, owner, category, ratings with reasons, controls, band and position.
  • The control evidence behind each residual score.
  • The treatment decisions for risks outside appetite, and the quarterly owner reviews that follow.

Assumptions

  • You are starting without a usable register, or replacing a list nobody maintains.
  • The figures shown are the defaults in the CISO Times risk management pack. Your own method may set different ones.

Not covered here